[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105647":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105647,781,1,"单选题","以下关于建设各方进度控制的主要任务的说法，错误的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","施工单位应按工程承包合同要求及时提供施工场地和图纸，并尽可能地改善施工环境",true,{"key":16,"text":17,"correct":18},"B","施工单位的任务是编制施工进度计划，并在计划执行过程中定期地、经常地通过实际进度与计划进度的检查、比较并实施调整",false,{"key":20,"text":21,"correct":18},"C","审批施工单位编制的施工进度计划是否符合施工合同工期管理约定属于监理工程师的任务",{"key":23,"text":24,"correct":18},"D","主要工程项目是否有遗漏，劳动力、材料、机械设备等是否满足进度要求也是属于监理工程师的任务","建设单位应按工程承包合同要求及时提供施工场地和图纸，并尽可能地改善施工环境，为工程施工的顺利进行开创条件。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]