[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105644":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105644,781,1,"单选题","计划工期属于（ ）阶段进度控制的目标。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","执行检查",false,{"key":16,"text":17,"correct":18},"B","编制计划",true,{"key":20,"text":21,"correct":14},"C","调整计划",{"key":23,"text":24,"correct":14},"D","方案定稿","施工过程中进度计划一般包括三个阶段，即编制计划、执行检查、调整计划；各个阶段进度控制的目标分别为：计划工期、偏差情况、调整内容。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]