[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105640":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105640,781,1,"单选题","当有若干个工程项目，或者将工程项目划分几个施工段或几个作业点时，建立若干个施工班组，分别同时按工艺顺序施工的作业方法是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","顺序作业法",false,{"key":16,"text":17,"correct":18},"B","平行作业法",true,{"key":20,"text":21,"correct":14},"C","流水作业法",{"key":23,"text":24,"correct":14},"D","连续作业法","当有若干个工程项目，或者将工程项目划分几个施工段或几个作业点时，建立若干个施工班组，分别同时按工艺顺序施工的作业方法。例如，上述3座涵洞，同时建立3个作业班组，同时按涵洞施工顺序开工的施工组织则是平行作业法。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]