[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105638":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105638,781,1,"单选题","不属于网络计划技术方法的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","关键线路法",false,{"key":16,"text":17,"correct":14},"B","计划评审方法",{"key":19,"text":20,"correct":14},"C","搭接网络计划",{"key":22,"text":23,"correct":24},"D","专家打分法",true,"网络计划技术有许多方法，主要有关键线路法（CPM）、计划评审方法（PERT）、流水作业网络计划、搭接网络计划（CNT）、图例评审法等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]