[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105636":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105636,781,1,"单选题","不属于施工准备过程内容的是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","项目施工组织机构及其人员配备与主要机械的计划与名单，是否进场或将于何日进场",false,{"key":16,"text":17,"correct":14},"B","用于工程的进口材料及机械、仪器和设备是否进场或将于何日进场，是否会影响施工进度，并提交进场计划及清单",{"key":19,"text":20,"correct":14},"C","用于本工程所在地的材料来源是否落实，并提交料源分布图及供料计划清单",{"key":22,"text":23,"correct":24},"D","物资、料具的采购",true,"服务施工过程：是指为施工生产过程和辅助工程及临时工程施工过程进行的各种服务工作，如物资、料具的采购、运输及保管等。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]