[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105633":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105633,781,1,"单选题","（ ）是施工组织的基本单位。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","工序",true,{"key":16,"text":17,"correct":18},"B","操作过程",false,{"key":20,"text":21,"correct":18},"C","人员",{"key":23,"text":24,"correct":18},"D","时间","由若干个在产品结构上密切联系的，能最终获得一种产品的施工过程的总和。相当于上述的分部工程或分项工程中的目。如挖路基或其中某一段落、一座桥梁、一条隧道等。但有些分项工程的施工过程不能分解为上述各个层次，但至少能分解到工序，所以工序是施工组织的基本单位。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]