[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105627":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105627,781,1,"单选题","（ ）是工程进度曲线规定的允许界限线。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","工程进度曲线",false,{"key":16,"text":17,"correct":14},"B","S曲线",{"key":19,"text":20,"correct":21},"C","进度管理曲线",true,{"key":23,"text":24,"correct":14},"D","前锋线","进度管理曲线是工程进度曲线规定的允许界限线，它指出了施工进度允许偏差范围所应满足的进度曲线变动区域。虽然组织突击赶工也可以按期交工，但这样做将会影响工程质量和经济效益，而进度管理曲线指出的安全区，不是组织突击赶工，而是在保证工期、质量和经济性的条件下，施工进度曲线规定的允许变动范围。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]