[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105625":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105625,781,1,"单选题","某分部工程有3个施工过程，分为4个施工段组织流水施工。各施工过程的流水节拍分别为3天、5天、4天、3天，3天、4天、4天、2天和4天、3天、3天、4天，则流水施工工期为（ ）天。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20",false,{"key":16,"text":17,"correct":14},"B","21",{"key":19,"text":20,"correct":14},"C","22",{"key":22,"text":23,"correct":24},"D","23",true,"本题考查的是公路工程施工组织方法和特点。 施工过程Ⅰ 3 8 12 15 施工过程Ⅱ 3 7 11 13 施工过程Ⅲ 4 7 10 14 K1，2=max{3，5，5，4，－13}=5； K2，3=max{3，3，4，3，－14}=4； T=ΣK+Σtn=（4+5）+14=23。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]