[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105622":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105622,781,1,"单选题","工作面的大小表明（ ）。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","能划分施工段的多少",false,{"key":16,"text":17,"correct":14},"B","空间位置的多少",{"key":19,"text":20,"correct":21},"C","能安排施工人数或机械台数的多少",true,{"key":23,"text":24,"correct":14},"D","能完成工程量的多少","本题考查的是公路工程施工组织方法和特点。工作面大小要求紧前工序结束后能为紧后工序提供工作面，且应满足施工技术规范和安全操作规程的要求。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]