[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105616":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105616,781,1,"单选题","桥梁基础工程包括开挖、支摸、浇筑混凝土及回填四个施工过程，分3个施工段组织流水作业，流水节拍见下表，则该基础工程的流水施工工期为（ ）天。 流水节拍（单位：天）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","17",false,{"key":16,"text":17,"correct":14},"B","20",{"key":19,"text":20,"correct":21},"C","23",true,{"key":23,"text":24,"correct":14},"D","24","本题考查的是公路工程施工组织方法和特点。 开挖 4，9，12 支模 3，6，10 浇筑混凝土 2，6，9 回填 4，8，11 K1.2=max{4，6，6，－10}=6 K2.3=max{3，4，4，－9}=4 K3.4=max{2，2，1，－11}=2 工期=6+4+2+11=23。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]