[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105614":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105614,781,1,"单选题","流水施工的基本组织方式包括（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","非节拍流水施工、有节拍流水施工",true,{"key":16,"text":17,"correct":18},"B","异节拍流水施工、等节拍流水施工",false,{"key":20,"text":21,"correct":18},"C","非节拍流水施工、等节拍流水施工",{"key":23,"text":24,"correct":18},"D","等节拍流水施工、有节拍流水施工","本题考查的是公路工程施工组织方法和特点。流水作业按其参数的特性可分为有节拍流水作业和无节拍流水作业两大类。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]