[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105611":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105611,781,1,"单选题","下列计算式中，对流水节拍的计算正确的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","流水节拍=工程量\u002F（每工日或每台班产量×施工班组人数或施工机械台班数）",true,{"key":16,"text":17,"correct":18},"B","流水节拍=工程量\u002F工程分段个数",false,{"key":20,"text":21,"correct":18},"C","流水节拍=工程量\u002F工程分包商个数",{"key":23,"text":24,"correct":18},"D","流水节拍=工程量\u002F工程施工时间×单位施工费用","本题考查的是公路工程施工组织方法和特点。流水节拍=工程量\u002F（每工日或每台班产量×施工班组人数或施工机械台班数）。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]