[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105602":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105602,781,1,"单选题","监理人在审批费用索赔时，应坚持的原则不含（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","自由心证原则",true,{"key":16,"text":17,"correct":18},"B","分级审批原则",false,{"key":20,"text":21,"correct":18},"C","恪守合同原则",{"key":23,"text":24,"correct":18},"D","公平合理原则","监理人在审批费用索赔时，应坚持以下原则： ①恪守合同原则。监理人在审批索赔时应严格按合同办事，在确认索赔是否成立时，首先应查实承包人的索赔是否有合同依据，是否是合同约定发包人应另行承担的赔偿责任。 ②尊重事实原则。监理人在审批索赔时应严格以事实为依据，凡是既有合同依据、又有损害事实的索赔应据实予以赔偿。 ③公平合理原则。监理人在审批索赔时应客观公正，既要尊重承包人索赔的权利，保护承包人在索赔中的合法权益，又要严格审查，防止承包人滥用索赔、虚夸事实、高估冒算等现象，做到合同依据充分，损害事实清楚，计算方法公平合理，计算结果可信。 ④分级审批原则。即监理人在审批索赔时，应严格遵守审批程序，逐级审查，分级把关，防止监理人员滥用权力的现象，保证索赔审批结果客观公正。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]