[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105598":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105598,781,1,"单选题","变更工程单价的首要依据是（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","采用计日工单价作计价依据",false,{"key":16,"text":17,"correct":14},"B","对工程量清单中的相应单价进行变更",{"key":19,"text":20,"correct":14},"C","协商确定新工程子目的单价",{"key":22,"text":23,"correct":24},"D","采用工程量清单中相应工程子目的单价",true,"采用工程量清单中相应工程子目的单价是变更工程单价的首要依据，即工程量清单中有相应工程子目者，原则上应按工程量清单中相应的工程子目单价来确定变更工程的单价。由于工程量清单的价格是承包人投标时填报的，用于变更工程，容易为发包人、承包人及监理人所接受，而且从合同意义上来说也比较公平合理。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]