[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105595":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105595,781,1,"单选题","发包人在工程量清单中给定的用于支付必然发生但暂时不能确定价格的材料的金额称为（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","暂估价",true,{"key":16,"text":17,"correct":18},"B","暂列金额",false,{"key":20,"text":21,"correct":18},"C","生产费用",{"key":23,"text":24,"correct":18},"D","特定估价","“暂估价”指发包人在工程量清单中给定的用于支付必然发生但暂时不能确定价格的材料、设备以及专业工程的金额。在工程招标阶段已经确定的材料、工程设备或工程项目，但又无法在当时确定准确价格，而可能影响招标效果时，发包人在工程量清单中给定一个暂估价。因此，暂估价是用于支付必然发生但暂时不能确定价格的材料、设备以及专业工程的金额。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]