[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105591":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105591,781,1,"单选题","路基填筑工程，当填料中石料含量（ ）时，按利用土石混填算。",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","小于30%",false,{"key":16,"text":17,"correct":14},"B","大于70%",{"key":19,"text":20,"correct":21},"C","大于30%、小于70%",true,{"key":23,"text":24,"correct":14},"D","小于70%","路基填筑工程或改河、改渠、改路填筑工程中，当填料中石料含量小于30%时，应按利用土方算，当填料中石料含量大于70%时，应按利用石方算，当填料中石料含量大于30%、小于70%时，应按利用土石混填算。填前压实、地面下沉增加的填方量按填料来源计量。需注意的是，满足施工需要，预留路基宽度宽填的填方量不另行计量。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]