[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105541":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105541,781,1,"单选题","当效益费用比BCR（ ）时，投资方案在经济上可以接受。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","≥1",true,{"key":16,"text":17,"correct":18},"B","＜1",false,{"key":20,"text":21,"correct":18},"C","＞1",{"key":23,"text":24,"correct":18},"D","≤1","效益费用比（BCR）是投资项目的全部效益现值和与全部费用现值和之比。当BCR≥1时，投资方案在经济上是可以接受的；BCR＜1时，则投资方案在经济上应予拒绝。BCR反映的是在基准折现率条件下，投资项目单位费用现值所带来的效益现值的大小，但它不能反映效益现值总额与费用现值总额之间的绝对差异，因而不一定能保证投资者资金有最大的增长。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]