[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105480":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105480,781,1,"单选题","公路工程验收规范中，以下不属于特别严重问题的合同段的是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","路基工程的大段落路基沉陷.大面积高边坡失稳",false,{"key":16,"text":17,"correct":18},"B","路面工程车辙深度大于10mm的路段累计长度超过该合同段车道总长度的3%",true,{"key":20,"text":21,"correct":14},"C","特大桥梁主要受力结构需要或进行过加固.补强",{"key":23,"text":24,"correct":14},"D","隧道工程渗漏水经处治效果不明显,衬砌出现影响结构安全裂缝，衬砌厚度合格率小于90%","本题考查的是质量评定与验收。选项B，路面工程车辙深度大于10mm的路段累计长度超过该合同段车道总长度的5%。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]