[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105454":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105454,781,1,"单选题","监理工程师应审查施工单位提交的施工测量放线数据和成果，对从基准点引出的工程控制桩的重点桩位应复测不少于（ ），经复测不符合规定时应要求其重新测设。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","20%",false,{"key":16,"text":17,"correct":14},"B","25%",{"key":19,"text":20,"correct":14},"C","28%",{"key":22,"text":23,"correct":24},"D","30%",true,"本题考查的是公路工程施工质量监理的阶段划分与内容。监理工程师应审查施工单位提交的施工测量放线数据和成果，对从基准点引出的工程控制桩的重点桩位应复测不少于30%，经复测不符合规定时应要求其重新测设。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]