[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105396":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105396,781,1,"单选题","电缆线路工程质量控制要求，不符合规定的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","目前主要采用充油、全塑型市话电缆",false,{"key":16,"text":17,"correct":14},"B","电缆线路工程的控制重点是敷设和接续两个工序",{"key":19,"text":20,"correct":21},"C","电缆的弯曲半径应大于其电缆外径的20倍",true,{"key":23,"text":24,"correct":14},"D","敷设后电缆的两端头应密封防潮，防止电缆芯线裸露","通信电缆线路是程控交换业务电话传输线路，目前主要采用充油、全塑型市话电缆，电缆线路工程的控制重点是敷设和接续两个工序。 ①施工前，应对到场的电缆进行单盘测试，使其符合合同要求。 ②根据施工图设计要求调查了解电缆经路及人(手）孔情况,核实施工单位的电缆配盘是否合理。 ③电缆敷设应符合规范，电缆预留应符合设计及规范有关规定，电缆的弯曲半径应大于其电缆外径的15倍，敷设后电缆的两端头应密封防潮，防止电缆芯线裸露。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]