[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105374":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105374,781,1,"单选题","浆段长度，在极破碎岩层为（ ）。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","30～50m",false,{"key":16,"text":17,"correct":14},"B","15～30m",{"key":19,"text":20,"correct":14},"C","10～35m",{"key":22,"text":23,"correct":24},"D","5～10m",true,"洞内工作面预注浆是分段进行的，一次注浆段长度，在极破碎岩层为5～10m，在破碎岩层中为10～15m，在裂隙岩层中为15～30m，重复注浆可取30～50m。掘进长度为注浆长度的70%～80%，每段预留20%～30%作为下段注浆的止浆盘。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]