[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105367":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":22,"analysis":25},1105367,781,1,"单选题","按编制对象范围不同可分为施工组织设计、单位工程施工组织设计和（ ）三种。",[11,15,18,21],{"key":12,"text":13,"correct":14},"A","扩大初步施工组织设计",false,{"key":16,"text":17,"correct":14},"B","施工组织设计大纲",{"key":19,"text":20,"correct":14},"C","初步施工组织条件设计",{"key":22,"text":23,"correct":24},"D","分部分项工程施工组织设计",true,"按编制对象范围不同可分为三种：①施工组织总设计。施工组织总设计是以隧道为编制对象，以指导整个隧道施工全过程的各项施工活动的综合性文件。②单位工程施工组织设计。单位工程施工组织设计是以一个单位工程为编制对象。指导其施工全过程的各项施工活动的综合性文件。③分部分项工程施工组织设计。分部分项工程施工组织设计是以分项工程为编制对象。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]