[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105355":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105355,781,1,"单选题","预防洞口坍塌措施，不符合规定的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","边坡仰坡放线，自上而下逐段开挖，不得掏底开挖或上下重叠开挖。",false,{"key":16,"text":17,"correct":18},"B","宜采用深眼大爆破开挖边（仰）坡",true,{"key":20,"text":21,"correct":14},"C","洞口支挡工程应结合土石方开挖一并完成。",{"key":23,"text":24,"correct":14},"D","边坡仰坡放线，自上而下逐段开挖，不得上下重叠开挖","(1)隧道开挖进洞前应尽早完成洞口排水系统,按设计要求进行边坡仰坡放线，自上而下逐段开挖，不得掏底开挖或上下重叠开挖。 (2)清除洞口上方可能滑塌的表土、树木及危石等;石质地段爆破后，应及时清除松动石块，土质地段开挖后应及吋夯实整平边（仰）坡。 (3)不得采用深眼大爆破开挖边（仰）坡，开挖的土石方不得弃在危害边仰坡稳定的地点，洞口支挡工程应结合土石方开挖一并完成。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]