[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105353":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":19,"analysis":25},1105353,781,1,"单选题","隧道防水设施施工监理事项，施工注意事项，不符合规定的是（）",[11,15,18,22],{"key":12,"text":13,"correct":14},"A","库房温度不高于40℃",false,{"key":16,"text":17,"correct":14},"B","外拼接塑料板,工作人员必须穿清洁的软底鞋，搬运时严禁沿地面拖拉",{"key":19,"text":20,"correct":21},"C","防水卷材倒放堆码整洁",true,{"key":23,"text":24,"correct":14},"D","塑料板施焊表面必须保证洁净、无灰尘和油脂等污物;如有油脂,应用丙酮洗净","施工注意事项。 ①防水卷材存放库房应整洁、干燥、无火源，自然通风要好，库房温度不高于40℃，存放时应立放，不得倒放堆码。 ②洞外拼接塑料板,工作人员必须穿清洁的软底鞋，搬运时严禁沿地面拖拉;塑料板上不得搁置焊枪，不得扔弃烟头及火柴梗等。 ③塑料板施焊表面必须保证洁净、无灰尘和油脂等污物;如有油脂,应用丙酮洗净。 ④立拱架、安模板、浇筑混凝土时应防止撞碰和刮破防水板;挡头板的支撑物在接触塑料板处必须加橡皮垫层;预埋的管件与塑料板的间距不应小于125px;绑扎钢筋和浇筑混凝土时，应有专人跟班观察,若发现防水板损伤立即修补。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]