[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105342":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105342,781,1,"单选题","箱梁体需分二次浇筑时，第一次和第二次浇筑的时间应间隔至少（ ）小时。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","12",false,{"key":16,"text":17,"correct":18},"B","24",true,{"key":20,"text":21,"correct":14},"C","36",{"key":23,"text":24,"correct":14},"D","48","若箱梁体不能一次浇筑完成，需分二次浇筑时，第一次浇筑到梁底板的承托顶部以上30cm。第一次和第二次浇筑的时间应间隔至少24h。在第二次浇筑前，应检查脚手架有无收缩和下沉，并打紧各楔块，以保证最小的压缩和沉降。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]