[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105300":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105300,781,1,"单选题","用平地机拌和时，每一作业段的长度宜为（ ）m。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","300～500",true,{"key":16,"text":17,"correct":18},"B","500～700",false,{"key":20,"text":21,"correct":18},"C","700～900",{"key":23,"text":24,"correct":18},"D","900～1000","用平地机拌和时，每一作业段的长度宜为300～500m。其中，平地机拌和时要注意以下几点：①拌和时，平地机刀片的安装角度宜符合规定；②使用符合级配要求的天然砂砾时，应用平地机进行补充拌和；③用平地机将拌和均匀的混合料按规定的路拱进行整平和整型；④用拖拉机、平地机和轮胎压路机在已初平的路段上快速碾压一遍，以暴露潜在的不平整；⑤再用平地机进行整平和整型。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]