[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105287":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105287,781,1,"单选题","沥青贯入式路面施工顺序是（ ）。",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","撒料→碾压→浇洒第一层沥青→撒布第一层嵌缝料→再碾压",true,{"key":16,"text":17,"correct":18},"B","撒料→碾压→浇洒第一层嵌缝料→撒布第一层沥青→再碾压",false,{"key":20,"text":21,"correct":18},"C","碾压→撒料→浇洒第一层嵌缝料→撒布第一层沥青→再碾压",{"key":23,"text":24,"correct":18},"D","撒料→浇洒第一层嵌缝料→碾压→撒布第一层沥青→再碾压","本题考查的是沥青面层施工质量监理。沥青贯入式路面施工顺序：（1）施工准备；（2）撒料；（3）碾压；（4）浇洒第一层沥青；（5）撒布第一层嵌缝料；（6）再碾压；（7）浇洒第二层沥青→撒布第二层嵌缝料→碾压→浇洒第三层沥青→撒布封层料→最后碾压（宜采用6～8t压路机碾压2～4遍）；（8）交通控制及初期养护",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]