[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105240":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":12,"analysis":25},1105240,781,1,"单选题","下列情况应进行试验段施工，监理工程师要做好审查，并严格审批试验段开工报告，描述错误的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","三级及三级以上公路路堤",true,{"key":16,"text":17,"correct":18},"B","填石路堤、土石路堤",false,{"key":20,"text":21,"correct":18},"C","特殊路基",{"key":23,"text":24,"correct":18},"D","拟采用新技术、新工艺、新材料、新设备的路","下列情况应进行试验段施工，监理工程师要做好审查，并严格审批试验段开工报告。 ①二级及二级以上公路路堤。 ②填石路堤、土石路堤。 ③特殊填料路堤。 ④特殊路基。 ⑤拟采用新技术、新工艺、新材料、新设备的路基。 ⑥其他监理工程师指示需要试验段的路基。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]