[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105233":3},{"question":4,"library":26},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":16,"analysis":25},1105233,781,1,"单选题","水准点复测与加密应符合下列规定，描述错误的是（）",[11,15,19,22],{"key":12,"text":13,"correct":14},"A","同一建设项目应采用同一高程系统，并应与相邻项目高程系统相有接",false,{"key":16,"text":17,"correct":18},"B","沿线每1000m宜有一个水准点",true,{"key":20,"text":21,"correct":14},"C","高速公路、一级公路宜加密，每200m—个水准点",{"key":23,"text":24,"correct":14},"D","在结构物附近、高填深挖路段、工程量集中及地形复杂路段，宜增设水准点","水准点复测与加密应符合下列规定： ①水准点精度应符合要求。 ②同一建设项目应采用同一高程系统，并应与相邻项目高程系统相有接。 ③沿线每500m宜有一个水准点。高速公路、一级公路宜加密，每200m—个水准点。在结构物附近、高填深挖路段、工程量集中及地形复杂路段，宜增设水准点。临时水准点应符合相应等级的精度要求，并与相邻水准点闭合。 ④对可能受施工影响的水准点，要求施工前应加固或改移，并应保持其精度。 ⑤水准点应进行不定期检查和定期复测，复测周期应不超过6个月，监理工程师应做好抽检。",{"id":6,"name":27,"category":28,"favorite":29},"目标控制（交通工程）","建筑工程",0]