[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105925":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105925,780,2,"多选题","根据《国务院关于投资体制改革的决定》，对于采用资本金注入方式的政府投资工程，政府需要审批（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","资金申请报告",false,{"key":16,"text":17,"correct":18},"B","项目建议书",true,{"key":20,"text":21,"correct":14},"C","工程开工报告",{"key":23,"text":24,"correct":14},"D","施工组织设计",{"key":26,"text":27,"correct":18},"E","可行性研究报告","BE","考点:投资决策阶段工作内容。对于采用直接投资和资本金注入方式的政府投资工程，政府需要从投资决策的角度审批项目建议书和可行性研究报告，除特殊情况外，不再审批开工报告，同时还要严格审批其初步设计和概算；对于采用投资补助、转贷和贷款贴息方式的政府投资工程，则只审批资金申请报告。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]