[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105899":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105899,780,2,"多选题","重大工程和技术复杂工程的工程设计工作一般划分为（）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","专项施工方案设计",false,{"key":16,"text":17,"correct":18},"B","初步设计阶段",true,{"key":20,"text":21,"correct":14},"C","施工组织设计",{"key":23,"text":24,"correct":18},"D","技术设计阶段",{"key":26,"text":27,"correct":18},"E","施工图设计阶段","BDE","2020版教材P11 本题考查的是工程建设程序。工程设计工作一般划分为两个阶段，即初步设计和施工图设计。重大工程和技术复杂工程，可根据需要增加技术设计阶段。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]