[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105882":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105882,780,2,"多选题","根据《国务院关于投资体制改革的决定》，下列工程只需审批资金申请报告的有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","采用投资补助方式的政府投资工程",true,{"key":16,"text":17,"correct":18},"B","采用资本金注入方式的政府投资工程",false,{"key":20,"text":21,"correct":14},"C","采用贷款贴息方式的政府投资工程",{"key":23,"text":24,"correct":18},"D","采用银行货款方式的企业投资工程",{"key":26,"text":27,"correct":18},"E","采用直接投资方式的政府投资工程","AC","本题考查的是投资决策阶段工作内容。采用投资补助、转贷和贷款贴息方式：只审批资金申请报告。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]