[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105755":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105755,780,2,"多选题","(2019年真题)根据《建筑法》，建设单位领取施工许可证后，还应按照国家有关规定办理申请批准手续的情形包括（）",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","临时占用规划批准范围以内的场地",false,{"key":16,"text":17,"correct":14},"B","拆除场地内的旧建筑物",{"key":19,"text":20,"correct":21},"C","进行爆破作业",true,{"key":23,"text":24,"correct":21},"D","临时中断道路交通",{"key":26,"text":27,"correct":21},"E","可能损坏电力电缆","CDE","建设单位领取施工许可证后，应当按照国家有关规定办理申请批准手续:①需要临时占用规划批准范围以外场地的;②可能损坏道路、管线、电力、邮电通讯等公共设施的:③需要临时停水、停电、中断道路交通的;④需要进行爆破作业的;⑤法律、法规规定需要办理报批手续的其他情形。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]