[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105722":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105722,780,2,"多选题","(2016年真题)项目监理机构控制工程进度的主要工作包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","审查施工方案",false,{"key":16,"text":17,"correct":18},"B","审查施工总进度计划和阶段性施工进度计划",true,{"key":20,"text":21,"correct":18},"C","检查施工进度计划的实施情况",{"key":23,"text":24,"correct":14},"D","对实际进度过快的工序下达停工令",{"key":26,"text":27,"correct":18},"E","比较分析工程施工实际进度与计划进度","BCE","工程进度控制的内容包括：审查施工单位报审的施工总进度计划和阶段性施工进度计划；检查施工进度计划的实施情况；比较分析工程施工实际进度与计划进度，预测实际进度对工程总工期的影响等。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]