[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105720":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105720,780,2,"多选题","根据《建设工程监理规范》，监理单位对设备制造单位质量管理体系的审查内容包括（ ）。",[11,15,18,22,25],{"key":12,"text":13,"correct":14},"A","设备制造单位报送的设备制造生产计划和工艺方案",true,{"key":16,"text":17,"correct":14},"B","设备制造的检验计划和检验要求",{"key":19,"text":20,"correct":21},"C","审核设备制造过程的检验结果，并检查和监督设备的装配过程",false,{"key":23,"text":24,"correct":14},"D","设备制造的原材料的质量证明文件及检验报告",{"key":26,"text":27,"correct":21},"E","设备制造单位报送的设备制造结算文件","ABD","考点:《建设工程监理规范》相关内容。项目监理机构应检查设备制造单位的质量管理体系，审查内容包括：设备制造单位报送的设备制造生产计划和工艺方案，设备制造的检验计划和检验要求，设备制造的原材料、外购配套件、元器件、标准件，以及坯料的质量证明文件及检验报告等。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]