[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105565":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105565,780,2,"多选题","项目监理机构控制工程进度的主要工作包括()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","审查施工方案",false,{"key":16,"text":17,"correct":18},"B","审查施工总进度计划和阶段性施工进度计划",true,{"key":20,"text":21,"correct":18},"C","检查施工进度计划的实施情况",{"key":23,"text":24,"correct":14},"D","对实际进度进行调整",{"key":26,"text":27,"correct":18},"E","比较分析工程施工实际进度与计划进度","BCE","(7)分包工程开工前，项目监理机构应审核施工单位报送的分包单位资格报审表。 (8)项目监理机构宜根据工程特点、施工合同、工程设计文件及经过批准的施工组织设计对工程风险进行分析，并提出工程质量、造价、进度目标控制及安全生产管理的防范性对策。 2.工程质量控制 3.工程造价控制 4.工程进度控制 5.安全生产管理的监理工作",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]