[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105241":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105241,780,2,"多选题","(2018年真题)根据《建设工程监理合同（示范文本）》，监理人需完成的基本工作有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","主持图纸会审和设计交底会议",false,{"key":16,"text":17,"correct":18},"B","检查施工承包人的试验室",true,{"key":20,"text":21,"correct":18},"C","查验施工承包人的施工测量放线成果",{"key":23,"text":24,"correct":18},"D","审核施工承包人提交的工程款支付申请",{"key":26,"text":27,"correct":18},"E","编写工程质量评估报告","BCDE","选项A错误，正确表述应该是：参加由委托人主持的图纸会审和设计交底会议。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]