[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105150":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105150,780,2,"多选题","(2016年真题)建设工程采用施工总承包模式的主要缺点有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建设周期较长",true,{"key":16,"text":17,"correct":18},"B","协调工作量大",false,{"key":20,"text":21,"correct":18},"C","质量控制较难",{"key":23,"text":24,"correct":18},"D","合同管理较难",{"key":26,"text":27,"correct":14},"E","投标报价较高","AE","施工总承包模式的缺点是：建设周期较长；施工总承包单位的报价可能较高。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]