[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105067":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105067,780,2,"多选题","(2016年真题）实行施工总承包的工程，专项施工方案可由专业分包单位组织编制的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","起重机械安装",true,{"key":16,"text":17,"correct":14},"B","起重机械拆卸",{"key":19,"text":20,"correct":14},"C","附着式升降脚手架",{"key":22,"text":23,"correct":24},"D","主体结构工程施工",false,{"key":26,"text":27,"correct":14},"E","深基坑开挖","ABCE","起重机械安装拆卸工程、深基坑工程、附着式升降脚手架等专业工程实行分包的，其专项施工方案可由专业分包单位组织编制。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]