[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105042":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105042,780,2,"多选题","根据《建设工程监理规范》，除常规监理工作方法外，监理工程师还可采用的工作方法有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","指令文件",true,{"key":16,"text":17,"correct":18},"B","平行检验",false,{"key":20,"text":21,"correct":18},"C","见证取样",{"key":23,"text":24,"correct":14},"D","监理通知",{"key":26,"text":27,"correct":14},"E","支付控制手段","ADE","考点:监理实施细则主要内容。监理工程师通过旁站、巡视、见证取样、平行检测等监理方法，对专业工程作全面监控，对每一个专业工程的监理实施细则而言，其工作方法必须加以详尽阐明。除上述四种常规方法外，监理工程师还可采用指令文件、监理通知、支付控制手段等方法实施监理。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]