[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105023":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105023,780,2,"多选题","下列选项中，监理规划应明确的工程进度控制措施有()。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立多级网络计划体系",true,{"key":16,"text":17,"correct":18},"B","严格审核施工组织设计",false,{"key":20,"text":21,"correct":14},"C","建立进度控制协调制度",{"key":23,"text":24,"correct":18},"D","该施工合同及时支付合同款",{"key":26,"text":27,"correct":14},"E","监控施工单位实施作业计划","ACE","2020教材P109-122 工程进度控制具体措施: 1) 组织措施:落实进度控制的责任，建立进度控制协调制度。 2) 技术措施:建立多级网络计划体系，监控施工单位的实施作业计划。 3) 经济措施:对工期提前者实行奖励;对应急工程实行较高的计件单价;确保资金的及时供应等。 4) 合同措施:按合同要求及时协调有关各方的进度，以确保建设工程的形象进度。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]