[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1105016":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1105016,780,2,"多选题","监理规划中明确的工程进度控制技术措施有( )。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","建立多级网络计划体系",true,{"key":16,"text":17,"correct":18},"B","严格审核施工组织设计",false,{"key":20,"text":21,"correct":18},"C","建立进度控制协调制度",{"key":23,"text":24,"correct":18},"D","按施工合同条款及时支付工程款",{"key":26,"text":27,"correct":14},"E","监控施工单位的实施作业计划","AE","2020教材P109-122 工程进度控制的技术措施:建立多级网络计划体系，监控施工单位的实施作业计划。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]