[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104992":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104992,780,2,"多选题","根据《建设工程监理规范》GB\u002FT 50319-2013，关于工程进度控制的具体措施包括的是（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确保资金的及时供应",true,{"key":16,"text":17,"correct":18},"B","严格质量检查和验收，不符合合同规定质量要求的，拒付工程款",false,{"key":20,"text":21,"correct":18},"C","对原设计或施工方案提出合理化建议并被采用，由此产生的投资节约按合同规定予以奖励",{"key":23,"text":24,"correct":14},"D","建立多级网络计划体系，监控施工单位的实施作业计划",{"key":26,"text":27,"correct":18},"E","协助完善质量保证体系","AD","本题考查的是监理规划主要内容。工程进度控制的具体措施：（1）组织措施：落实进度控制的责任，建立进度控制协调制度。（2）技术措施：建立多级网络计划体系，监控施工单位的实施作业计划。（3）经济措施：对工期提前者实行奖励；对应急工程实行较高的计件单价；确保资金的及时供应等。（4）合同措施：按合同要求及时协调有关各方的进度，以确保建设工程的形象进度。选项BE是工程质量控制具体措施；选项C是工程造价控制具体措施",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]