[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104959":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104959,780,2,"多选题","(2018年真题）项目监理机构对监理单位内部检测设备需求进行协调平衡时应注意的内容有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","规格的明确性",true,{"key":16,"text":17,"correct":14},"B","数量的准确性",{"key":19,"text":20,"correct":14},"C","质量的规定性",{"key":22,"text":23,"correct":14},"D","期限的及时性",{"key":25,"text":26,"correct":27},"E","使用的规范性",false,"ABCD","本题考查的是组织协调。对建设工程监理检测试验设备的平衡。建设工程监理开始实施时，要做好监理规划和监理实施细则的编写工作，合理配置建设工程监理资源，要注意期限的及时性、规格的明确性、数量的准确性、质量的规定性。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]