[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104952":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104952,780,2,"多选题","(2017年真题）项目监理机构在施工阶段进度控制的任务有（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","完善建设工程控制性进度计划",true,{"key":16,"text":17,"correct":18},"B","审查施工单位专项施工方案",false,{"key":20,"text":21,"correct":18},"C","审查施工单位工程变更申请",{"key":23,"text":24,"correct":14},"D","制定预防工期索赔措施",{"key":26,"text":27,"correct":14},"E","组织召开进度协调会","ADE","本题考查的是目标控制。项目监理机构在建设工程施工阶段进度控制的主要任务是通过完善建设工程控制性进度计划、审查施工单位提交的进度计划、做好施工进度动态控制工作、协调各相关单位之间的关系、预防并处理好工期索赔，力求实际施工进度满足计划施工进度的要求",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]