[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104950":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104950,780,2,"多选题","(2015年真题）项目监理机构在施工阶段造价控制的主要任务有（ ）。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","预防并处理费用索赔",true,{"key":16,"text":17,"correct":14},"B","挖掘降低造价潜力",{"key":19,"text":20,"correct":14},"C","控制工程付款",{"key":22,"text":23,"correct":14},"D","控制工程变更费用",{"key":25,"text":26,"correct":27},"E","确定造价控制目标",false,"ABCD","项目监理机构在建设工程施工阶段造价控制的主要任务是：通过工程计量、工程付款控制、工程变更费用控制、预防并处理好费用索赔、挖掘降低工程造价潜力等使工程实际费用支出不超过计划投资。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]