[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104944":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104944,780,2,"多选题","(2010年真题）下列监理任务中，属于施工阶段质量控制任务的有（ ）。",[11,15,18,21,25],{"key":12,"text":13,"correct":14},"A","审查确认总承包单位资质",true,{"key":16,"text":17,"correct":14},"B","审查施工组织设计",{"key":19,"text":20,"correct":14},"C","审查确认分包单位资质",{"key":22,"text":23,"correct":24},"D","做好工程变更方案的比选",false,{"key":26,"text":27,"correct":14},"E","审核竣工图","ABCE","本题考核三大目标控制任务中，建设工程质量控制任务。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]