[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104943":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104943,780,2,"多选题","(2011年真题）建设工程目标控制的组织措施包括（ ）。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","确定建设工程发包组织管理模式",false,{"key":16,"text":17,"correct":18},"B","明确目标控制人员的任务和职能分工",true,{"key":20,"text":21,"correct":18},"C","建立健全目标控制机构与相关人员",{"key":23,"text":24,"correct":18},"D","改善目标控制工作流程",{"key":26,"text":27,"correct":14},"E","对技术方案组织技术经济分析论证","BCD","本题考核三大目标控制措施中的组织措施内容。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]