[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104919":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104919,780,2,"多选题","根据《建设工程监理规范》GB／T 50319—2013，总监理工程师应及时签发《工程暂停令》的有()。",[11,15,18,21,24],{"key":12,"text":13,"correct":14},"A","施工单位违反工程建设强制性标准的",true,{"key":16,"text":17,"correct":14},"B","建设单位要求暂停施工且工程需要暂停施工的",{"key":19,"text":20,"correct":14},"C","施工存在重大质量、安全事故隐患的",{"key":22,"text":23,"correct":14},"D","施工单位未按审查通过的工程设计文件施工的",{"key":25,"text":26,"correct":27},"E","施工单位未按审查通过的施工方案施工的",false,"ABCD","2020教材P135-137 项目监理机构发现下列情况之一时，总监理工程师应及时签发工程暂停令: (1) 建设单位要求暂停施工且工程需要暂停施工的; (2) 施工单位未经批准擅自施工或拒绝项目监理机构管理的; (3) 施工单位未按审查通过的工程设计文件施工的; (4) 施工单位违反工程建设强制性标准的; (5) 施工存在重大质量、安全事故隐患或发生质量、安全事故的。 D选项属于项目监理机构应签发《监理通知单》的情形。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]