[{"data":1,"prerenderedAt":-1},["ShallowReactive",2],{"q-1104889":3},{"question":4,"library":30},{"id":5,"libraryId":6,"type":7,"typeLabel":8,"stem":9,"options":10,"answer":28,"analysis":29},1104889,780,2,"多选题","为了有效地控制建设工程三大目标，需要逐级分解建设工程总目标，按（ ）等制定分目标、子目标及可执行目标，形成建设工程目标体系。",[11,15,19,22,25],{"key":12,"text":13,"correct":14},"A","工程项目时间进展",true,{"key":16,"text":17,"correct":18},"B","工程质量控制",false,{"key":20,"text":21,"correct":18},"C","工程造价控制",{"key":23,"text":24,"correct":14},"D","工程参建单位",{"key":26,"text":27,"correct":14},"E","工程项目组成","ADE","本题考查的是目标控制。为了有效地控制建设工程三大目标，需要逐级分解建设工程总目标，按工程参建单位、工程项目组成和时间进展等制定分目标、子目标及可执行目标，形成建设工程目标体系。",{"id":6,"name":31,"category":32,"favorite":33},"监理概论","建筑工程",0]